The project


This project involves infrastructure work on the third section of Line 15 between Pont-de-Sèvres and Villejuif-Louis Aragon.

  • Length: 12 km
  • 8 passenger stations with an average depth of 36 m
  • 12 related works (shafts) with an average depth of 40 m
  • 3 tunnellers
  • 12 towns connected in 2 departments (Hauts-de-Seine and Val-de-Marne).